Replacing water main on 107th Avenue
FTLComm - Tisdale - Wednesday, August 4, 2010
This year work has begun on 107th Avenue between 99th and 98th Street. The pavement has to be removed on the south side of the street then the whole block will be excavated removing the old cast pipe and replacing it with plastic.
Since this is a street the backfilling is extremely important. First the new line is backfilled with gravel which is packed during the process then the fill material is replaced and packed layer by layer back down so that there will be a minimal amount of settling in the first two years. The top layer of backfill is gravel to form a street base.
It is the normal practice to let the street lie in this gravel state for at least a year and sometime two or more before the street is repaved.