Floor Pouring

FTLComm - Tisdale
August 5, 1999


It is interesting to watch a project grow from a business plan to reality and the Car / truckwash being developed on the South side of town has been steadily progressing. We first showed you the site as it was being cleared, then as the structure was assembled now here it stands with a roof and crews working to install the underfloor drainage and concrete flooring.


This is the scene this morning around 8:30 as Chupa Excavation is busy moving gravel around, Little's RediMix is pouring cement and workers were scurying around to keep up with the project, laying pipe and moving the pouring cement into place.